tnd4Tundra Torquay 16-09 frac

AWARDED Mon, Jun 22

Details

Tundra Oil & Gas SK cemented-liner frac on well Torquay (16-09) Hz 01-04-002-11W2 (Torquay formation). Frac Crew 1. This is well 4 of 4 in the program — the large 105-stage well the 2026-05-20 pre-qual checklist was filled for.

  • Well: Torquay (16-09) Hz 01-04-002-11W2 / UWI 101/01-04-002-11W2/00 / Surface LSD 02/16-09-002-11W2
  • Formation: Torquay
  • Frac parameters: 105 stages (KB*), 15 t/stage (1,575 t total), 7 m³/min, 5,038.27 m lateral, FL-65 sleeve
  • AFE: 20260116CM (REL); License 411460; Planned TD 5,038.27 m
  • Tracer: N/A on Tundra's schedule
  • Matches the 2026-05-20 pre-qual PDF: 114.3 mm × 17.26 kg/m P-110 LT&C liner, TVD 2,000 m / TMD 6,300 m, 105 stages, annular O-C-O same run, max rate 5 m³/min (note: Tundra's schedule says 7 m³/min — verify which value Kobold operations should use), max treating pressure 45 MPa, BHT ~65 °C estimated, sweet (<0.5% H2S).
  • Open verification items inherited from the pre-qual: BHT vs. ≥ 90 °C trigger discrepancy; "2000 MPa" toe-port pressure unit; planned rate discrepancy (5 vs 7 m³/min).

Who's involved

Geoff Puckett Mark King Owen Rush Paul Vos Jeff Kennedy Tundra Oil & Gas Kobold

Current state

  • Status: awarded
  • Confidence: Date sourced from Tundra's 2026-05-15 SK frac schedule issued by Mark King (AFE status REL, GWID 22151). current_date 2026-06-22 = the frac finish date (no post-frac follow-on row in the schedule), per Jeff's "latest date after drilling" rule. Pre-qual completion is a soft prerequisite — Kobold form D000065 v5 is filled for this well's parameters; the in-person pre-qual is still TBD per Paul Vos.

Discrepancies (4)

  • Planned rate: pre-qual PDF says 5 m³/min, Tundra schedule says 7 m³/min. Confirm with Owen Rush which value Kobold ops should use.
  • Toe-port pressure listed as "2000 MPa" on the pre-qual PDF — physically implausible. Likely a unit error (2000 kPa = 2 MPa, or 200 MPa). Verify with the form author.
  • BHT estimated ~65 °C on the pre-qual but the ≥ 90 °C trigger threshold is referenced elsewhere — confirm whether any HT-rated equipment is actually needed for this well.
  • Schedule was updated on 2026-06-05 (see inbox/2026-06-05 Email Jeff Kennedy - Tundra Sask Frac Schedule Jun05). Verify `current_date` against the new XLSX — the value here came from the superseded 2026-05-15 schedule.

Sources (4)

email 2026-06-05 Email Jeff Kennedy - Tundra Sask Frac Schedule Jun05 2026-06-05 21:32 UTC moves
Said by: [[Jeff Kennedy]] <[email protected]>
(Jeff forwarded with no added body — pass-through. Mark King's original distribution:) > Good day everyone, here is the Sask Frac Schedule > > Mark > King > Senior Completions Technician, Completions > Tundra Oil & Gas > 295 3rd Ave., Virden, Manitoba R0M 2C0 > T: 204-748-4455 | [email protected]
email 2026-05-21 Email Mark King Tundra - Sask Directional Plans 2026-05-21 21:48 UTC mentions SUPERSEDED
Claims date: May 21
Said by: Mark King <[email protected]> (forwarded by Paul Vos, then Jeff Kennedy)
From: King, Mark <[email protected]> Sent: Thursday, May 21, 2026 12:09:15 PM To: Paul Vos; Owen Rush Cc: Keating, Ryan Subject: Sask Directional Plans As requested. Mark King — Senior Completions Technician, Completions Tundra Oil & Gas — 295 3rd Ave., Virden, Manitoba R0M 2C0 T: 204-748-4455 | [email protected]
email 2026-05-21 Email Jeff Kennedy - Tundra SK frac schedule 2026-05-21 00:02 confirms
Said by: Jeff Kennedy <[email protected]>
I'm forwarding this email with an attachment from Tundra. There's a list of four upcoming confirmed jobs with dates and some well information and formation. Please create events for them based on the latest date after the drilling, and make them separate events.
email 2026-05-20 Email Jeff Kennedy - Tundra Torquay frac pre-qual 2026-05-20 23:58 proposes CURRENT
Claims date: June
Said by: Jeff Kennedy <[email protected]>
We have two jobs for Tundra coming up in the Torquay region. Attached is a pre-job qualification that lists all the information for these two wells: depth, stage count, temperature, and all the rest of it. Let's plan for these to be in mid-June. I'll send updated dates in a subsequent spreadsheet with all the rest of Tundra's jobs.