tnd2Tundra Steelman 08-30 frac
Details
SK cemented-liner frac on well Steelman (08-30) Hz 09-29-004-03W2 (Marly formation). Frac Crew 1.
- Well: Steelman (08-30) Hz 09-29-004-03W2 / UWI 101/09-29-004-03W2/00 / Surface LSD 00/08-30-004-03W2
- Formation: Marly
- Frac parameters: 25 stages, 5 t/stage (125 t total), 1 m³/min, 2,901.12 m lateral, FL-100 sleeve
- AFE: 20260113CM (FAPP); License 408303; Planned TD 2,901.12 m
- Tracer: N/A on Tundra's schedule
Who's involved
Mark King Owen Rush Jeff Kennedy Tundra Oil & Gas Kobold
Current state
- Status: awarded
- Confidence: Date sourced from Tundra's 2026-05-15 SK frac schedule issued by (AFE status FAPP, GWID 22047).
current_date2026-06-06 = the frac finish date (no post-frac follow-on row in the schedule), per Jeff's "latest date after drilling" rule.
Discrepancies (1)
- Schedule was updated on 2026-06-05 (see ). Verify `current_date` against the new XLSX — the value here came from the superseded 2026-05-15 schedule.
Sources (3)
email
2026-06-05 21:32 UTC
moves
Said by: [[Jeff Kennedy]] <[email protected]>
(Jeff forwarded with no added body — pass-through. Mark King's original distribution:) > Good day everyone, here is the Sask Frac Schedule > > Mark > King > Senior Completions Technician, Completions > Tundra Oil & Gas > 295 3rd Ave., Virden, Manitoba R0M 2C0 > T: 204-748-4455 | [email protected]
email
2026-05-21 21:48 UTC
mentions
SUPERSEDED
Claims date: May 21
Said by: Mark King <[email protected]> (forwarded by Paul Vos, then Jeff Kennedy)
From: King, Mark <[email protected]> Sent: Thursday, May 21, 2026 12:09:15 PM To: Paul Vos; Owen Rush Cc: Keating, Ryan Subject: Sask Directional Plans As requested. Mark King — Senior Completions Technician, Completions Tundra Oil & Gas — 295 3rd Ave., Virden, Manitoba R0M 2C0 T: 204-748-4455 | [email protected]
email
2026-05-21 00:02
confirms
Said by: Jeff Kennedy <[email protected]>
I'm forwarding this email with an attachment from Tundra. There's a list of four upcoming confirmed jobs with dates and some well information and formation. Please create events for them based on the latest date after the drilling, and make them separate events.