tnd1Tundra Alameda 16-19 frac

AWARDED Thu, Jun 4

Details

Tundra Oil & Gas SK cemented-liner frac on well Alameda (16-19) Hz 16-20-004-03W2 (Vuggy formation). Frac Crew 1.

  • Well: Alameda (16-19) Hz 16-20-004-03W2 / UWI 101/16-20-004-03W2/00 / Surface LSD 00/16-19-004-03W2
  • Formation: Vuggy
  • Frac parameters: 25 stages, 5 t/stage (125 t total), 1 m³/min, 2,897.65 m lateral, FL-100 sleeve
  • AFE: 20260112CM (FAPP); License 406662; Planned TD 2,897.65 m
  • Tracer: N/A on Tundra's schedule

Who's involved

Mark King Owen Rush Jeff Kennedy Tundra Oil & Gas Kobold

Current state

  • Status: awarded
  • Confidence: Date sourced from Tundra's 2026-05-15 SK frac schedule issued by Mark King (AFE status FAPP, GWID 22042). current_date 2026-06-04 = the latest post-frac row's finish per Jeff's "latest date after drilling" instruction. Frac proper finishes 2026-05-29; the trailing 6-day row (2026-05-29 → 2026-06-04) is post-frac follow-on activity.

Discrepancies (1)

  • Schedule was updated on 2026-06-05 (see inbox/2026-06-05 Email Jeff Kennedy - Tundra Sask Frac Schedule Jun05). Verify `current_date` against the new XLSX — the value here came from the superseded 2026-05-15 schedule.

Sources (3)

Conflict. Current target 2026-06-04 is set manually in the event's frontmatter; no source below confirms it. A source references May 21. Add a source for the current target, or update the frontmatter to match the sources.
email 2026-06-05 Email Jeff Kennedy - Tundra Sask Frac Schedule Jun05 2026-06-05 21:32 UTC moves
Said by: [[Jeff Kennedy]] <[email protected]>
(Jeff forwarded with no added body — pass-through. Mark King's original distribution:) > Good day everyone, here is the Sask Frac Schedule > > Mark > King > Senior Completions Technician, Completions > Tundra Oil & Gas > 295 3rd Ave., Virden, Manitoba R0M 2C0 > T: 204-748-4455 | [email protected]
email 2026-05-21 Email Mark King Tundra - Sask Directional Plans 2026-05-21 21:48 UTC mentions SUPERSEDED
Claims date: May 21
Said by: Mark King <[email protected]> (forwarded by Paul Vos, then Jeff Kennedy)
From: King, Mark <[email protected]> Sent: Thursday, May 21, 2026 12:09:15 PM To: Paul Vos; Owen Rush Cc: Keating, Ryan Subject: Sask Directional Plans As requested. Mark King — Senior Completions Technician, Completions Tundra Oil & Gas — 295 3rd Ave., Virden, Manitoba R0M 2C0 T: 204-748-4455 | [email protected]
email 2026-05-21 Email Jeff Kennedy - Tundra SK frac schedule 2026-05-21 00:02 confirms
Said by: Jeff Kennedy <[email protected]>
I'm forwarding this email with an attachment from Tundra. There's a list of four upcoming confirmed jobs with dates and some well information and formation. Please create events for them based on the latest date after the drilling, and make them separate events.