sa5fSaturn Flat Lake Bromhead-Hoffer 04-16 pad frac

TENTATIVE Sun, Oct 11

Details

Saturn Flat Lake program, final pad: surface location 04-16-003-12W2. 1 Torquay well. Frac tentatively 2026-10-11. Last pad of the 10-well, 600-stage Flat Lake program.

Well: 101/04-04-003-12W2, Torquay, spud 14-Sep-26, frac 11-Oct-26. 60 stages × 15 t.

Who's involved

Josh Graham Owen Rush Paul Vos Jeff Kennedy Saturn Kobold

Current state

  • Status: tentative
  • Confidence: "Very tentative" per Josh Graham 2026-05-20.

Sources (1)

Conflict. Current target 2026-10-11 is set manually in the event's frontmatter; no source below confirms it. A source references May 20. Add a source for the current target, or update the frontmatter to match the sources.
email 2026-05-21 Email Jeff Kennedy - Saturn Flat Lake schedule 2026-05-21 21:48 UTC proposes SUPERSEDED
Claims date: May 20
Said by: Josh Graham <[email protected]> (forwarded by Owen Rush, then Jeff Kennedy)
From: Josh Graham <[email protected]> Sent: Wednesday, May 20, 2026 2:05:24 PM To: Owen Rush Subject: Re: [EXTERNAL] Flat Lake Wells Hey Owen, Very tentative timing below for Flat Lake. | Area | Bottomhole UWI | Surface Location | Formation | Estimated Spud Date | Estimated Frac Date | Estimated Stage Count | Tonnage | |---|---|---|---|---|---|---|---| | Bromhead/Hoffer | 101/14-24-001-16W2/00 | 03-13-001-16W2 | Torquay | 21-May-26 | 22-Jul-26 | 60 | 15 | | Bromhead/Hoffer | 101/15-24-001-16W2/00 | 03-13-001-16W2 | Torquay | 3-Jun-26 | | 60 | 15 | | Bromhead/Hoffer | 101/01-01-001-16W2/00 | 03-13-001-16W2 | Bakken | 16-Jun-26 | | 60 | 15 | | Bromhead/Hoffer | 101/03-01-001-16W2/00 | 03-13-001-16W2 | Bakken | 29-Jun-26 | | 60 | 15 | | Bromhead/Hoffer | 101/16-22-001-15W2/00 | 04-14-001-15W2 | Torquay | 12-Jul-26 | 17-Aug-26 | 60 | 15 | | Bromhead/Hoffer | 101/04-02-001-15W2/00 | 04-14-001-15W2 | Torquay | 25-Jul-26 | | 60 | 15 | | Bromhead/Hoffer | 101/13-33-001-14W2/00 | 07-21-001-14W2 | Torquay | 7-Aug-26 | 30-Aug-26 | 60 | 15 | | Bromhead/Hoffer | 102/14-12-003-12W2/00 | 03-01-003-12W2 | Torquay | 20-Aug-26 | 24-Sep-26 | 60 | 15 | | Bromhead/Hoffer | 102/02-26-002-12W2/00 | 03-01-003-12W2 | Torquay | 2-Sep-26 | | 60 | 15 | | Bromhead/Hoffer | 101/04-04-003-12W2/00 | 04-16-003-12W2 | Torquay | 14-Sep-26 | 11-Oct-26 | 60 | 15 | Cheers, Josh Graham, P.Eng — Senior Operations Engineer O: (403) 693-4878 | M: (403) 901-9654 | E: [email protected]