# Raw email — Tundra SK frac schedule forward (4 confirmed wells)

**From:** Jeff Kennedy <jeffkennedy@koboldinc.com>
**To:** benagenttesting@gmail.com
**Received:** 2026-05-21 00:02 UTC
**Gmail thread id:** 19e47d758670746e

## Body

```
I'm forwarding this email with an attachment from Tundra. There's a list of four upcoming confirmed jobs with dates and some well information and formation. Please create events for them based on the latest date after the drilling, and make them separate events.

----- Forwarded -----
From: Owen Rush <owenrush@koboldinc.com>
Sent: May 20, 2026 5:55 PM
To: Jeff Kennedy
Subject: Fw: Sask Frac Schedule

(forward only)

----- Forwarded -----
From: King, Mark <mark.king@tundraoilandgas.com>
Sent: Wednesday, May 20, 2026 9:53:47 AM
To: (Tundra Sask frac service vendor distribution list)
Cc: tdebacker@innovativeals.ca; McClymont, Rick
Subject: Sask Frac Schedule

Hello Everyone, this is our plan for Sask cemented liner fracs.

Mark
```

## Attachments

- [2026-05-20 Tundra 2026_Q3-Q4_CompletionsSchedule_May15_SaskFrac.xlsx](2026-05-20%20Tundra%202026_Q3-Q4_CompletionsSchedule_May15_SaskFrac.xlsx) — Tundra completions schedule, Frac Crew 1 sheet.

## Schedule extract (4 wells)

| # | Well | Surface LSD | UWI | Formation | Rig release | Frac start | Frac finish | Latest post-drill date | Stages | Tonnage/stage (t) | Total tonnage (t) | Rate (m³/min) | Lateral (m) | Sleeve | GWID |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Alameda (16-19) Hz 16-20-004-03W2 | 00/16-19-004-03W2 | 101/16-20-004-03W2/00 | Vuggy | 2026-05-22 12:00 | 2026-05-27 | 2026-05-29 (frac) → 2026-06-04 (post-frac, 6 d) | **2026-06-04** | 25 | 5 | 125 | 1 | 2,897.65 | FL-100 | 22042 |
| 2 | Steelman (08-30) Hz 09-29-004-03W2 | 00/08-30-004-03W2 | 101/09-29-004-03W2/00 | Marly | 2026-05-31 12:00 | 2026-06-04 | 2026-06-06 | **2026-06-06** | 25 | 5 | 125 | 1 | 2,901.12 | FL-100 | 22047 |
| 3 | Torquay (13-09) Hz 14-16-002-11W2 | 01/13-09-002-11W2 | 101/14-16-002-11W2/00 | Torquay | 2026-05-28 08:00 | 2026-06-06 | 2026-06-08 (frac) → 2026-06-18 (post-frac, 10 d) | **2026-06-18** | 50 KB* | 15 | 750 | 7 | 3,748.46 | FL-65 | 22003 |
| 4 | Torquay (16-09) Hz 01-04-002-11W2 | 02/16-09-002-11W2 | 101/01-04-002-11W2/00 | Torquay | 2026-06-11 08:00 | 2026-06-18 | 2026-06-22 | **2026-06-22** | 105 KB* | 15 | 1,575 | 7 | 5,038.27 | FL-65 | 22151 |

Notes from the spreadsheet:
- Frac Crew 1 is the assigned crew for all 4.
- AFE status: FAPP for wells 1 and 2; REL for wells 3 and 4.
- Tracer column reads "N/A" on every row.
- Wells 3 and 4 (Torquay) are tied to the 2026-05-20 pre-qual forward — the 105-stage pre-qual PDF matches well 4 (16-09).

"Latest date after drilling" interpretation per Jeff's instruction: take the finish date of the last scheduled row for each well (frac finish, or the post-frac follow-on row where present). Used as `current_date` on each per-well event.